Fair Oaks Ranch Project

 
 

COMMITMENT TO RELIABLE SERVICE
In an effort to continuously improve the delivery and reliability of electric service to our community, we are performing a multi-phase project to help mitigate the risk of power outages in the Fair Oaks Ranch area.

 

SCOPE OF PROJECT 
The work consists of extensive tree trimming near overhead lines and removing or replacing aging equipment. As phases of our work are completed, area residents can expect to see an improvement to the reliability of their electric service.

 

ESTIMATED TIMELINE
The powerline maintenance and tree trimming is in progress and is expected be completed by the end of April 2019.  A construction project to add another circuit is expected to be completed in Summer 2019.

                                                                                                                                                                        

PROJECT UPDATES

Fall 2018

• Developed maintenance plan to improve reliability

• Repaired defective device

 

February 2019

• Completed inspection of powerline for condition of equipment and vegetation

• Completed main line maintenance and tree trimming